Pan Gulf Technologies Engineering Services

Steel Case Study - Station Parking Garage

Get to know more about the project below

Play Video

PGT SCOPE:

Model Creation in SDS/2, Structural Steel detailing for Main & Misc. Steel

SOFTWARE USE:

SDS/2

TONNAGE:

Apprx. 200

PROJECT DELIVERABLES:

3D Model in SDS/2, Erection, Shop Drawings & Gather drawings., BOM , KISS / NC Files

PROJECT DESCRIPTION:

Project is a 4-story parking garage in U.S. This parking garage is meant for commuters using the RTD Metro in U.S.

SOLUTION PROVIDED BY PGT:

Project was a muti-story parking structure for the metro line at 104th station in U.S. It was a fast-paced project with majority of PGT scope being in the miscellaneous steel. PGT actively participated in Coordination with other trades for timely delivery and completed project on schedule.

CHALLENGES:

Fast paced projects with majority of our work in miscellaneous steel as our scope meant, PGT had to be agile and proactive in making sure there were no issues related to coordination from other trades since the start of the projects. Actively participating in coordination meetings and pursuing pressing RFIs, seeking clarifications on conflicting information, we were able to speed up our miscellaneous steel detailing without slow down while covered in time with the main steel scope with the overall project completed within agreed schedule, save for few last minutes changes in design.

Get in touch with our

Expert’s Today!