Redevelopment of an old commercial center site to create a company headquarters campus. The development included the demolition of office blocks and the construction of 6-storey office buildings over three levels of basement.
Preparation of RC Shop Drawings along with BBS for the following:
01. Foundations
02. Basement to Sixth-Floor Slab
03. Columns
04. Core Walls
05. Retaining Walls
06. Roof-Level Slabs
07. Metal Decks
- AutoCAD with CADS-RC
01. 3D Model in SDS/2
02. Erection & Shop Drawings
03. BOM
04. KISS/NC Files
Challenges:
The project had a tight deadline that needed to be met quickly. We had to prepare RC shop drawings and other BBS as mentioned in the scope above. We applied our expertise and teamwork to complete the job successfully.
Solutions:
Given the short timeframe, we created and shared a delivery schedule, splitting the project work in such a way that both the customer and Pan Gulf could work and share mark-ups simultaneously, without impacting the deliverable milestones or quality.